101 Franklin Street

Location

Manhattan, NY

Owner

Skylight, Cannon Hill, & TPG

Client

UAG

project overview

new foundation for office to residential conversion

101 Franklin Street in Tribeca sat empty for close to a decade when developers decided to convert the property from an office building to 72 luxury condominiums. This included adding four floors, which takes the property from 17 to 21 stories.

ECD’s scope covers everything beneath the building to support the new addition: deep foundations, temporary bracing of the existing foundation walls, and the new concrete and waterproofing that make up the cellar. The new loads are carried by 56 minicaissons, each drilled to bedrock.

Minicaissons installed

lf – pile length

the challenge

drilling to bedrock under low headroom

On most sites, a rig works under open sky and runs long lengths of casing into the ground in one go. At 101 Franklin the building stayed up the whole time. Every pile had to be installed from inside the existing cellar, with the floor slab just overhead and columns and pile caps on every side.

the solution

short sections, full depth

The ceiling height limited how much casing the rig could take at once. Our crews installed each minicaisson in 5- to 10-foot sections of casing, splicing them together on the way down.

Working around what stays

Every pile was placed between columns, pile caps and walls that supported the building. That took compact equipment, careful sequencing and tight control of each pile’s location.

Holding the existing foundation

Lowering a full cellar takes away soil the old foundation walls lean on. We braced them with steel strongbacks tied back into the existing structure, so they held their position the whole way down.